Integration Plan (RTB Older Integrations)

Document created by pubmatic-archivist on Mar 27, 2017Last modified by catherine.racette on Jun 7, 2017
Version 2Show Document
  • View in full screen mode

Note: This document supports a set of APIs for older integrations.

The PubMatic integration plan is as follows:

  1. Review and implement the RTB API specification
  2. Fill out the  Technical Questionnaire
  3. Plan your integration timeline
  4. Integration Testing
  5. Release

Step 1: API Specification

Review the API Specification and get technical clarifications.

Step 2: Technical Questionnaire

Obtain the Technical Questionnaire from your PubMatic Account Manager, fill it out, and send it back to us.

Step 3: Plan Your Integration Timeline

Share your timeline for API Service Implementation, Integration Testing, and planned API Integration Release Date.

Step 4: Integration Testing

Prerequisites:

  1. Technical Questionnaire should be filled out and returned (at least 2 weeks prior to integration testing )
  2. Unit tested API Service should be available
  3. Working creative URL/ad tag (PSA ads are good enough)

Testing:

  1. Functionality:
    • test with correct request/response
    • test with invocation of Creative URL/ad tag to see whether ad loads correctly
    • test the click tracking mechanism
    • test the reports to validate the calls made, revenue (bid values), clicks made
  2. Performance:
    • test request/response timing (should be <75ms)q
  3. Load:
    • test with multiple request/response in parallel
      (upto peak load of ~1800 requests per second as of now)
  4. Exception:
    • test with missing/mal framed/delayed request, response

 

Planned Testing Phases: 

 

    1. Phase 1 [request, response, parameters validation]
      Test only request/response format and validation of all mandatory parameters.
      - No real impressions/bid value involved.
      - This can happen even on a non-production server once your software is ready.
      - timeline : 1-2 days
      - less than 5,000 imps per day
       
    2. Phase 2 [with test impressions, test ads]
      - Test on production server with test impressions
      - Test feature, performance, timeout, throughput and load
      - Validate the API, ad serving, cookie, tracking mechanism at both ends
      - timeline : 2-3 days
      - 50K Impressions each with 50, 100, 200, 300 requests in parallel

 

  1. Phase 3 [test with real impressions, real ads, Demand Partner pays for the impressions]
    - test on production server with real impressions [low volume]
    - test feature, performance, timeout, throughput and load
    - validate the ad serving, cookie, tracking mechanism at both ends
    - verify the reporting figures at both ends
    - timeline : 3 days of testing and 2-3 days for validation of reports
    [ Demand Partner pays for the winning impressions]
    - less than 100,000 imps per day

Step 5: Release

After successful API Integration Testing, PubMatic shall release the API service for Integration with RTB traffic from PubMatic.